Field Deployment case study
Proof: Regenerative NOx removal

86% average NOx removalacross 55 loading days.

Krajete operated a 250 L pilot adsorber on real waste-incineration flue gas, progressively stabilised the gas-conditioning train, and demonstrated the full concept from adsorption through thermal regeneration to recovery of high-purity nitric acid. The ca

Client & context

Waste-to-energy · Delfzijl, the Netherlands · Incineration flue gas · 124 days of field operation, 2025–2026

The problem, with a number

Variable NOx in wet incineration flue gas, where condensation, moisture carry-over, flow stability and pressure balance decided real performance.

What we measured

Inlet and outlet NOx, temperature and flow in the field; segmented bed sampling and total-nitrogen analysis on the material afterwards.

What we did

Ran a 250 L adsorber at 60–70 m³/h, exchanged material at breakthrough, then regenerated off-site and recovered the nitrogen as liquid.

What the campaign
had to handle

Wet beds load less

Wet lower bed zones showed lower effective nitrate loading, and therefore reduced adsorber utilisation.

A long, shared supply line

The gas supply depended on an upstream CO₂-purification unit and needed stable pressure and flow across a long line.

Seasons changed the result

Seasonal temperature swings influenced removal; cool, non-oversaturated inlet gas proved essential.

A first-of-a-kind field setup

Early operation exposed excessive condensation, moisture-sensitive flow measurement and upstream pressure anomalies.

Conditioning before chemistry

The challenge was never adsorption alone: drainage, demisting and pressure balance had to be solved first.

Recovery, not destruction

The project aimed to recover nitrogen as nitric acid or nitrate solution, not merely destroy or dilute NOx.

How was a four-month field campaign run?

Step 01

Rebuild the supply

Extended metallic line, added drainage points, removed flow restrictions and fitted an interstage support fan.

Step 02

Measure through moisture

A moisture-robust flow meter, with temperature and water controlled so oversaturated gas never entered the vessel.

Step 03

Load to breakthrough

Successive campaigns at 60–70 m³/h, exchanging material at breakthrough and mapping nitrate across the bed.

Step 04

Regenerate and recover

Staged external heat, upstream condensation, and scrubbing of remaining NOx into a nitrate-bearing solution.

The oven process was an exploratory ex-situ development setup, not the recommended final industrial regeneration architecture.

What the instruments recorded

The segmented third regeneration recovered about 26.2% of the nitrate inventory under deliberately incomplete, static ex-situ conditions. The report treats that as a test-method result, not a final industrial recovery limit.

METRIC recorded basis
Total field operation 124 days More than four accumulated months across three loading phases
Campaign average 78% average Recorded overall average in the pilot performance summary
Loading 2 42 days at 70% removal Consecutive operation with largely linear saturation behaviour
Loading 3 55 days at 86% removal 76 calendar days including a 21-day maintenance interruption
Peak spot performance 99.6% 23.1 ppm inlet and 0.1 ppm outlet on 10 October 2025
Dry-bed nitrate loading 4.1% average Peak upper-zone values of about 6.3–6.4 wt.%
Optimised acid product 0.5–0.6 M About 31–40 g/L nitric acid; no detected metals, very low organic carbon

What the campaign looked like

Chart Krajete Field measurement

Loading three, day by day

Fifty-five active days at 86% average removal, across 76 calendar days that included a 21-day maintenance stop.

Chart Krajete Regeneration

When the nitrogen came off

NOx release accelerated sharply above about 340 °C headspace temperature during ex-situ thermal regeneration.

Lab picture Krajete

NOx REMOVED.

NITROGEN
RECOVERED.

Delfzijl, the Netherlands. Captured nitrogen recovered as high-purity nitric acid, at 0.5–0.6 M.

86%

average NOx removal during the final 55 active loading days

124 days

accumulated real-flue-gas field operation

0.5–0.6 M

optimised high-purity nitric-acid condensate

What the pilot was worth
commercially

Predictable saturation

The second and third loadings developed largely linearly once gas conditioning was under control.

Longer service intervals

Active loading duration rose from 27 days to 42, and then to 55.

Product quality

Optimised condensates contained no detected metals and only a few mg/L of organic carbon.

The economic levers

Moisture management, contact time and regeneration temperature emerged as the primary engineering and economic levers.

A circular pathway

The recovered liquids showed the potential to replace a waste stream with a clean nitrogen-containing product.

No ROI is claimed

No realised ROI, disposal saving or product revenue was documented. The demonstrated value is technical de-risking and a credible circular-product pathway.

What the scale-up needs

Three loading phases and three ex-situ regenerations resolved the core chemistry and exposed the limits of static oven regeneration. The report recommends an integrated adsorption–regeneration–recovery pilot as the next step.

ELEMENT DESIGN BASIS EVIDENCE STATUS
Adsorption contact GHSV ideally ≤ 600 h⁻¹ Measured basis and recommendation.
Inlet and moisture Below 40 °C, ideally below 30 °C, no oversaturation Recommendation and critical measured lesson: engineer drainage and demisting.
Regeneration Above 300 °C in the static test setup Measured ex-situ finding. The industrial concept is a controlled hot-purge with condensation and scrubbing — recommended, not yet built.

What has to be proven before
commercial acceptance?

Measured evidence covers the field adsorption campaign and three exploratory ex-situ regenerations. Source: EEW Pilot Plant Campaign final report, 6 May 2026.

Next 01

Close the nitrogen balance

Across inlet gas, outlet gas, loaded solid, regenerated solid, condensate and scrubber liquid.

Next 02

Define the operating cycle

Breakthrough criteria, regeneration endpoints, product targets, energy demand and acceptable NOx slip.

Next 03

Replace the static oven

Controlled dynamic heat and mass transfer, verified over repeated cycles, with active HSE controls for rapid NOx release.

NOx IS NOT WASTE.

IT IS NITROGEN.

Discuss your flue-gas profile, outlet target and regeneration concept with a Krajete engineer. See regenerative NOx removal